    Wards Road Bridge Improvements

    Wards Road Bridge Improvements

    The Wards Road Bridge Improvement Project is a rehabilitation.  It involves minor rehabilitation of the deck and painting of the structural steel components.  The improvements are the best management practices to prevent further deterioration and to reduce maintenance costs on this particular bridge.

         

     

    City of Lynchburg Representatives
    Project Manager Joe Smith 434-455-4449
    Construction Coordinator Joe Smith 434-455-4449
    Consultant / Designer / Engineering Firm / Project Inspector Schwartz & Associates, Inc. 434-237-6584
    Contractor Burleigh Construction 434-993-2214

     

    Project Timeline
    Design Phase January through February 2012
    Bid Phase October through November 2012
    Construction May through October 2013
    Project Close Out November through December 2013

     

    Current Posted Projects
    2012 Bridge Maintenance Project Lower Bluff Walk Phases II & III
    Bridge Safety Inspections Main Street Bridge / Gateway
    Fifth Street Phase II McConville Road Culvert
    Jefferson Street South / Lower Bluff Walk Phase I Rivermont Avenue Bridge
    Kemper Street Bridge Wards Road Bridge Improvements
    Lakeside Dr. / Park Ave. / Memorial Ave. Intersection  

     

    No votes yet