Project Schedule

The project will move in a linear block-by-block fashion, starting at Jackson Street and working uphill towards Taylor St. The utility work will be completed first in each phase and the streetscape work will follow after the waterlines are installed. The Park Avenue section will only have utility work (no extensive streetscaping will be done on this block) and the block between Monroe St. and Taylor Street on Fifth St. will only have streetscaping work completed (there is no utility work in that block). At the end of the project, the entire project area will be closed in order for the final asphalt to be installed.

Phase 1
Phase II
Phase III
Phase IV
Phase V