Liberty Mountain Phase III
The Liberty Mountain Drive Phase III project connects Liberty Mountain Drive (from the LU Natatorium and Track & Field Complex) to the newly constructed Odd Fellows Road interchange/roundabout.
This one mile road which will run parallel with 460E, will consist of 4,232 linear feet of new 12” waterline, along with curb, street lights, and storm system which will eventually settle into three permanent basins.
There will be a 10’ wide sidewalk built along one side of the new road to match the previous Phase II project. The project completion date is scheduled for October 2019.
![]() |
![]() |
Project Schedule & City of Lynchburg Representatives | |
---|---|
Anticipated Completion Date: | October 2019 |
Contractor: | Haymes Brothers, Inc. |
Project Manager: | Tim Worley |
City Project Manager: | Jason Ingram |