Link Road Bridge Replacement

Originally built in 1957, the existing Link Road Bridge is a one span bridge, with a concrete deck, steel beams, and concrete abutments. It measures 54’ in length with two 12’ wide lanes and no sidewalk. The replacement bridge will be lengthened to approximately 87’ long with two 15’ wide lanes. There will also be a sidewalk added on the downstream side of the bridge. The construction of the replacement bridge will include a concrete deck, pre-stressed concrete bulb tee beams, semi-integral backwalls, and concrete abutments on steel piles.

Project amount: $3,210,160        Project is an eight month contract. 

Project Schedule & City of Lynchburg Representatives
Project Advertisement: September 14, 2020
Bid Opening: October 13, 2020
Anticipated Start Date: November 30, 2020
Anticipated Completion Date: August 1, 2021
Project Owner: Public Works Department
City Project Manager: Seth Campbell
Contractor: TBD